Nvidia Cuts OpenAI Data Center Guarantee to Under $120B, WSJ Says
Nvidia now expects to initially guarantee less than $120 billion for OpenAI's Ohio data center project, down from $250 billion, after investors questioned its risk exposure, the WSJ reported.
TL;DR
- Nvidia now expects to initially guarantee less than $120 billion for OpenAI's planned Ohio data center, down from $250 billion, the Wall Street Journal reported [^1].
- The cut followed investor concerns about Nvidia's risk exposure and leaves open who backs the rest of the 10-gigawatt project [^1] [^2].
Background
Reuters says the Ohio project would help OpenAI move toward owning AI infrastructure, though its ability to fund large commitments is under scrutiny because it is unprofitable despite an $852 billion valuation [^1]. A financial backstop, or guarantee, is a promise to cover a borrower's debt if the borrower can't pay. OpenAI has no investment-grade credit rating, so lenders were being asked to price the debt against Nvidia's instead, The Next Web writes [^2].
What happened
On August 14, the Wall Street Journal reported, citing people familiar with the matter, that Nvidia had revised its plans to support a proposed OpenAI data center project in Ohio [^1]. The chipmaker is now expected to initially guarantee less than $120 billion, down from the $250 billion previously discussed. According to the Journal, the two companies were nearing an agreement in which Nvidia would provide a financial backstop only for the first phase, and a deal could be signed as early as that weekend [^1]. The Next Web, summarizing the report by the Journal's Anissa Gardizy, says Nvidia would initially back only half of the 10-gigawatt project and decide about the rest later [^2].
The Journal said the change was made after investors raised concerns about Nvidia's risk exposure tied to large financing commitments [^1]. The Next Web, which covered the $250 billion figure on July 27, the day after the Journal first reported it, notes that Nvidia shares fell 5% after that first report [^2]. Nvidia did not immediately respond to Reuters, and OpenAI declined to comment [^1].
OpenAI is still discussing a binding lease for the full 10 gigawatts. The site is being developed by SB Energy, a SoftBank subsidiary, and would be the largest data center project announced to date if completed [^1]. The Next Web puts a first phase of roughly 800 megawatts at completion in 2028 and the total cost at more than $500 billion once the chips are counted [^2]. A separate agreement to finance OpenAI's chip purchases could total $350 billion across the full project, money Nvidia would help arrange rather than guarantee outright [^2].
Why it matters
The size of the guarantee measures how much of its customer's risk the chipmaker is willing to carry. The Next Web reads the sequence plainly: the market priced the promise, disliked the price, and the promise shrank, while nothing about the Ohio campus itself changed in three weeks [^2]. It also points to an asymmetry. Nvidia's equity holdings appear in quarterly filings anyone can read, but a guarantee sits off the balance sheet until somebody calls it, so investors, in the publication's words, "priced the fear instead" [^2].
This is not the first time the partnership has been trimmed. Nvidia and OpenAI announced an agreement last September covering at least 10 gigawatts, with Nvidia investing up to $100 billion, and that deal stalled after some inside Nvidia expressed doubts [^2]. Nvidia is meanwhile trying to bring outside money into the build-out: earlier the same week, it partnered with six major financial institutions on compute financing platforms meant to raise more than $500 billion in third-party capital [^1]. The Next Web cautions that those are memorandums rather than committed money, and says the open question is who ends up guaranteeing the remaining 5 gigawatts, because that shows who carries the risk [^2].
Practical example
Say a friend asks you to co-sign the lease on a large apartment. The landlord agrees because of your credit, not your friend's, and if your friend stops paying, you owe the rent. That is roughly the role lenders were asking Nvidia to play for OpenAI's Ohio campus [^2]. Now say you agree to co-sign for only half of it and decide about the rest later. Your friend still wants the whole apartment, but the landlord has to find security for the other half somewhere else. That is the shape of the deal the Journal described: a backstop for the first part only, while OpenAI keeps negotiating a lease for all 10 gigawatts [^1] [^2].